History & Timeline

1990
Established with a capacity of 4000TPA of SBA/MEK.

1995
Certified with ISO: 9001

2000
Commencement of the manufacturing of hydrogenated products .

2002
Certified with ISO: 14001

2006
Certified with OHSAS 18001

2008
Capacity enhancement to 8000 TPA of SBA/MEK

2010
Capacity enhancement to 10000 TPA of SBA/MEK
Commissioning of spent acid recovery unit

2014
Capacity enhancement to 20000 TPA of SBA/MEK
Commissioning of Biomass cogeneration 2 MW captive power plant.

2015
Commissioning of Feed enrichment unit

2020
Upgradation to ISO:45001 standard

2022
Capacity enhancement to 22000TPA of SBA/MEK